Create a Website Account - Manage notification subscriptions, save form progress and more.
Letters to residents
36 Hour Development Letter
Contract Awarded: W.W. Payton
Contract Award Date: March 26, 2019
Project Estimated Completion Date: July 2021
Project Status: COMPLETE
Contract Award Budget: $3,150,000.00
Contract Information
Planned Water Outage
Contractor to Work May 29, 2021
Updated Project Plans
Letter to Residents 20210511
Phasing 1
Plans
Letters To Residents 20191018
Letter to Residents for Cleaning & CCTV Sewer Line
Brochure to Residents for Sewer Line Cleaning & CCTV
Construction Letter 20201201
Engineer: IDS Engineering Group
Notice to Proceed Date: May 10, 2021
Contract Award Date: December 15, 2020, Conrad Construction
Project Completion Date: April - May 2022
Contract Amount: $2,837,491.00
Sign up for Construction Updates
Phasing
Construction Letter 20201014
Construction Letter 20200727
Letters To Residents: CCTV
Contractor Info on Sewer Cleaning
Smoke Testing Letter
Smoke Testing Door Knocker
Video of the smoke testing process: https://youtu.be/j1xCvRx-mHc
Construction Communication
Engineer: Gessner Engineering
Notice To Proceed Date: October 26, 2020
Contract Award Date: August 25, 2020, Conrad Construction Company
Estimated Completion Date: June 2021
Contract Amount: $1,095,283
Letters/Communication To Residents:
Phasing:
Engineer: Binkley & Barfield
Notice to Proceed Date: June 6, 2022
Contract Award Date: April 26, 2022, MetroCity, LLC.
Estimated Completion Date: February 28, 2023
Contract Amount: $1,365,593.00
Updates/Letters To Residents
Bore Hole Locations for Street Base Determination
Project Status: CONSTRUCTION DESIGN PHASE 90% as of September 2022
Notice to Proceed Date: TBD
Contract Award Date: TBD
Estimated Start Date: 2023
Contract Amount:
Updates/Letters To Residents:
Engineer: CobbFendley
Project Status: PRE-DESIGN PHASE
Estimated Start Date: 2024