- Home
- Living In...
- Construction & Project Updates
Capital Improvement Projects (CIP)
Bond Issue 2
#4 Winningham, Cedarspur & Burkhart (East of Voss) Pavement & Utility Improvements
Letters/Communication To Residents:
- Initial Construction Letter to Residents
- Notice of Construction
- Door Hanger - Water Disconnect
- Door Hanger - Driveway Access
- Street Light Outage Letter - 10/07/2022
Phasing:
- Demo Phase 1
- Paving Sequence
- Phases 1 & 2 Complete
- Phases 3& 4 In Progress
Engineer: Binkley & Barfield
Notice to Proceed Date: June 6, 2022
Contract Award Date: April 26, 2022, MetroCity, LLC.
Estimated Completion Date: April 2023
Contract Amount: $1,365,593.00
#5 Cedarspur (West of Bingle), Burkhart (East of Bingle) Pavement & Utility Improvements
Updates/Letters To Residents
Bore Hole Locations for Street Base Determination
Engineer: Gessner Engineering
Project Status:
Town Hall Meeting: TBD
Notice to Proceed Date: TBD
Contract Award Date:
Estimated Start Date:
Contract Amount:
#6 Brighton Place (Winningham Lane; Burkhart Circle; Burkhart Court; Pech Rd.; Cedarspur Dr.; Krist Dr.) Pavement & Utility Improvements
Updates/Letters To Residents:
- 9/16/22: Surveying Notice
Engineer: CobbFendley
Project Status: Construction Design Phase at ~60%, 100% Design expected August 2023
Town Hall Meeting: TBD
Notice to Proceed Date: TBD
Contract Award Date: TBD
Estimated Start Date: 2024
Contract Amount:
New Production Water Well
Contract Awarded: W.W. Payton
Contract Award Date: March 26, 2019
Project Estimated Completion Date: July 2021
Project Status: COMPLETE
Contract Award Budget: $3,150,000.00
#2 Loeser, Traweek, Lone Star, & West Tex Pavement & Utility Improvements
Contractor to Work May 29, 2021
Letter to Residents for Cleaning & CCTV Sewer Line
Brochure to Residents for Sewer Line Cleaning & CCTV
Engineer: IDS Engineering Group
Notice to Proceed Date: May 10, 2021
Contract Award Date: December 15, 2020, Conrad Construction
Project Completion Date: April - May 2022
Project Status: COMPLETE
Contract Amount: $2,837,491.00
#3 Green Valley and Winningham (West) Pavement & Utility Improvements
Sign up for Construction Updates
Contractor Info on Sewer Cleaning
Video of the smoke testing process: https://youtu.be/j1xCvRx-mHc
Engineer: Gessner Engineering
Notice To Proceed Date: October 26, 2020
Contract Award Date: August 25, 2020, Conrad Construction Company
Estimated Completion Date: June 2021
Project Status: COMPLETE
Contract Amount: $1,095,283